Silent feature of Modernization &
Up-gradation (MTUP) Programme |
The following schemes have already
been commissioned |
w |
Capital outlay proposed = Rs 659 Crores |
|
w
Winder Upgradation |
|
w |
Two street Soap Stone Powder Feeding |
|
Name of the Schemes |
w |
Quality Control System for L&T machine |
|
w |
Multi-fuel FBC Boiler to strengthen Utilities |
|
w |
Multifuel AFBC Boiler at NPM |
|
w |
Modernization of Continuous Cooking Plant |
|
The following Schemes are under
execution stage |
w |
Revamping of the Pulping Line with Oxygen Delignification
Plant, Additional Chlorine Dioxide Manufacturing facility
and change to elemental Chlorine free Bleaching Sequence. |
|
w |
Multifuel AFBC Boiler at CPM |
w |
Cut Size Sheeter at CPM |
|
w |
Improving the Paper Machine QCS and size press for Quality
improvement and Improvement Machine Drive System. |
|
UNITWISE INVESTMENT |
CPM |
NPM |
|
Rs. 307 Crores |
Rs. 350 Crores |
|
|
w |
Up-gradation in Rewinding and cutting facility |
|
|
w |
Capacity enhancement by 30% at NPM |
|
|
w |
Associated Balancing facilities in Pulping and Paper Machine
area, Evaporator and Recovery Boiler Area |
|
|
w |
Installation of ESP for Coal Fired Boiler |
|
|
w |
Membrane Cell Conversion at Caustic Chlorine Plants |
|
|
w |
Online Coating facilities for Voith Machine at CPM |
|
|
w |
New Reel Wrapping Machine |
|
|